Update as of August 10
Saturday is the last day of paving and striping, meaning the parking lot will be fully opened Sunday.
IMPORTANT INFORMATION FOR SATURDAY:
- The main entrance and exit will continue to be fully operational and handicap parking spaces will stay at their usual locations.
- The Y South entrance and front section of the Y South parking lot will be blocked off for sealing and striping, and the back section of the Y South parking lot will be available via access through the main parking lot.
The City will be coming back soon to finish their part of the drive aisle, including the planters and raising the sewer access lids. We will do our best to keep you informed as we learn more.
We appreciate your continued understanding and patience.
----------------------------------
Update as of August 9
We are one day closer to our new parking lot being complete!
- Tomorrow, Friday, August 9, the main entrance and exit will be fully operational, so you can enter and exit as usual.
- Handicap parking spaces will be back to their usual locations, with access to the facility through the regular ADA ramp entrance.
- Y South parking will be restricted to the front section of the lot, as the back section will be closed for sealing and striping.
Additional parking spaces may be blocked off as parking lot work continues through Sunday, August 11.
--------------------------------------
We’re excited to announce that the City Easement Project through our driveway is almost complete. And, even better news, we will soon also have a freshly sealed parking lot!
We have been fortunate that the majority of the easement/drive aisle work has been conducted at night, however over the next 2 weeks there will be disruption to the normal traffic flow and a 3-day facility closure.
Monday, July 29 through Wednesday, July 31, the Y remains open normal hours. However, the main driveway will be closed for concrete and drive aisle repairs. How you enter and exit the facility will be impacted.
- To access the Y, you will need to use the Y South entrance.
- You will be able to park in the Y South lot or the Y North parking lot by the back fence.
- You will exit through Y South or Y North driveways.
Monday, August 5 through Wednesday, August 7 the Y facility will be closed, in order to dig out damaged areas of our parking lot. We regret having to ever close our facility because we know how much you and our entire community rely on the Y. We are limiting the closure to the minimum number of days necessary.
We will reopen on Thursday, August 8 at our normal time. Work on our 2 parking lots will continue through Sunday, August 11. Over the course of 4 days (Thursday, August 8 to Sunday, August 11) portions of the parking lot will be blocked off for sealing and striping. Clear directions through email and cones will be provided to guide you to available parking areas.
While we are closed, we will take this opportunity to do other maintenance and repairs. Here is what you can expect to be accomplished during the closure:
- Resurfacing of both parking lots
- Refinishing Studio 1 and Studio 2 hardwood floors
- Painting the Y South men’s locker room, Child Watch rooms, Café, and main hallway doors
- Replacing the shower floors in the outdoor women’s locker room
- Grinding necessary areas of the pool deck to help reduce slips and falls
- Removing old ice bearing units from Y North and Y South
- Performing fitness equipment maintenance
- High dusting of parts of the facility
- Continuing work on our Y South saunas, set for a September opening day
The next 2 weeks may be challenging and we appreciate your understanding and patience.